 Activity  Immediate  Predecessor (s)  Time  (weeks)  A3 BAC4DA2EA,B4 F A, B,C2GD,E1HE6IE,F2 JG,H,I4 KH,I3 LI6\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \mathrm { A } & \cdots & 3 \\\mathrm {~B} & - \mathrm { A } \\\mathrm { C } & \cdots & 4 \\\\\mathrm { D } & \mathrm { A } & 2 \\\mathrm { E } & \mathrm { A } , \mathrm { B } & 4 \\\mathrm {~F} & \mathrm {~A} , \mathrm {~B} , \mathrm { C } & 2 \\\\\mathrm { G } & \mathrm { D } , \mathrm { E } & 1 \\\mathrm { H } & \mathrm { E } & 6 \\\mathrm { I } & \mathrm { E } , \mathrm { F } & 2 \\\\\mathrm {~J} & \mathrm { G } , \mathrm { H } , \mathrm { I } & 4 \\\mathrm {~K} & \mathrm { H } , \mathrm { I } & 3 \\\mathrm {~L} & \mathrm { I } & 6 \\\hline\end{array}
-Using Table 3.7,suppose activity D can be shortened from 4 weeks to 1 week.Assume all other activity times remain the same.How much shorter will the total project earliest completion time become?


Definitions:

Industrial Countries

Nations with significant levels of industrialization, high standards of living, and advanced technological infrastructure.

Second Phase

Refers to a subsequent stage in a process or a series of developments, often implying a change or escalation from an initial condition.

Industrial Revolution

A period of major industrialization that took place during the late 1700s and early 1800s, leading to significant changes in agriculture, manufacturing, mining, transport, and technology.

Midlife Crisis

A period of emotional turmoil and identity questioning that can occur in middle adulthood, often associated with reevaluating one's life achievements, goals, and relationships.

Related Questions