You are responsible for managing a project with the following activities
(times are given in weeks) .
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 2514 B 81114 C 579 A  D 6912 A  E 135 D,B \begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 2 & 5 & 14 & \cdots \\\text { B } & 8 & 11 & 14 & \cdots \\\text { C } & 5 & 7 & 9 & \text { A } \\\text { D } & 6 & 9 & 12 & \text { A } \\\text { E } & 1 & 3 & 5 & \text { D,B } \\\hline\end{array}
-Using Table 3.10,what is the critical path and expected completion time for this project?


Definitions:

Job Performance

The level of effectiveness with which an individual executes their job-related tasks, responsibilities, and duties.

Job Analysis

The process of gathering, examining, and interpreting data about a job's tasks and responsibilities to determine what is required of an individual in that role.

Scientific-Management

A management theory focusing on improving economic efficiency, especially labor productivity, by scientifically studying work methods and setting performance standards.

Individual Initiative

The action of taking the first step or move without prompt from others, showcasing autonomy and proactivity.

Related Questions