Table 311
You Are Responsible for Managing a Project with the the

question 120

Multiple Choice

Table 3.11
You are responsible for managing a project with the
following activities (times are given in days) .
 Activity  Expected  Time  Immediate  Predecessor(s)   A 3 B 6 C 2 D 5 A  E 2 C  F 7 A  G 4 B,D,E \begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & \cdots \\\text { B } & 6 & - \cdots \\\text { C } & 2 & \cdots \\\text { D } & 5 & \text { A } \\\text { E } & 2 & \text { C } \\\text { F } & 7 & \text { A } \\\text { G } & 4 & \text { B,D,E } \\\hline\end{array}
-Using,Table 3.11,which of the following activities has the largest amount of slack?


Definitions:

Reaction

A chemical change that occurs when substances combine or decompose forming new compounds.

Boiling Point

The temperature at which a liquid’s vapor pressure equals the external pressure surrounding the liquid, causing it to turn into vapor.

Molecules

The smallest unit of a chemical compound that can exist, composed of two or more atoms bonded together chemically.

Compound Name

The designation of a chemical substance based on its composition and structure.

Related Questions