Table 313
You Are Responsible for Managing a Project with the the Following

question 20

Multiple Choice

Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
 Activity  Expected  Time  Immediate  Predecessor (s) A8 B 10 C 7 A,B  D 5 B  E 12 C  F 7 C,D  G 6 E,F  H 10 F \begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 8 & \cdots - \\\text { B } & 10 & - \\\text { C } & 7 & \text { A,B } \\\text { D } & 5 & \text { B } \\\text { E } & 12 & \text { C } \\\text { F } & 7 & \text { C,D } \\\text { G } & 6 & \text { E,F } \\\text { H } & 10 & \text { F } \\\hline\end{array}
-Using Table 3.13,if the expected time for activity E is decreased to 8 weeks,what is the new expected completion time for the project?


Definitions:

Strategic

Relating to the identification of long-term or overall aims and interests and the means of achieving them.

Developmental

Pertaining to growth or progress, often used in contexts relating to personal, professional, or organizational advancement.

Organizational Behavior Modification (OBM)

A plan for managing the behavior of employees through a formal system of feedback and reinforcement.

Informal System

An unstructured and unofficial means of operation within an organization, consisting of activities and communications that are not prescribed by formal rules, policies, or structures.

Related Questions