Consider the tasks,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow.
 Activity  Description  Immediate  Predecessor(s)  Optimistic  (Weeks)  Most Likely  (Weeks)  Pessimistic  (Weeks)  A 4710 B  A 2820 C  A 81216 D  B 123 E  D, C 6822 F  C 234 G  F 222 H  F 6810 I  E, G,H 4812 J  I 123\begin{array} { | c | c | c | c | c | } \hline \begin{array} { c } \text { Activity } \\\text { Description }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Optimistic } \\\text { (Weeks) }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { (Weeks) }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { (Weeks) }\end{array} \\\hline \text { A } & - \cdots & 4 & 7 & 10 \\\hline \text { B } & \text { A } & 2 & 8 & 20 \\\hline \text { C } & \text { A } & 8 & 12 & 16 \\\hline \text { D } & \text { B } & 1 & 2 & 3 \\\hline \text { E } & \text { D, C } & 6 & 8 & 22 \\\hline \text { F } & \text { C } & 2 & 3 & 4 \\\hline \text { G } & \text { F } & 2 & 2 & 2 \\\hline \text { H } & \text { F } & 6 & 8 & 10 \\\hline \text { I } & \text { E, G,H } & 4 & 8 & 12 \\\hline \text { J } & \text { I } & 1 & 2 & 3 \\\hline\end{array}
a.What is the expected time for activity B?
b.What is the variance for activity B?
c.Based on the calculation of estimated times,what is the critical path?
d.What is the estimated time of the critical path?
e.What is the activity variance along the critical path?
f.What is the probability of completion of the project before week 42? You will need to refer to a standard normal table to answer the question.


Definitions:

15-degree Angle

A measure of rotation that equals one-sixteenth of a complete circle's rotation; it's a small acute angle commonly used in geometry.

60-degree Angle

An angle measuring 60 degrees, often associated with equilateral triangles where all three interior angles are equal.

Productive Cough

A cough that expels mucus or phlegm from the respiratory tract, assisting in clearing the airways.

Short of Breath

The sensation of struggling to breathe or draw deep breaths, often indicative of respiratory conditions, cardiac issues, or exertion.

Related Questions