Table 33 -Using Table 3

question 107

Multiple Choice

Table 3.3
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 3 C 3 D  B 4 E  A,C 4 F  B 4 G  H  E 5 I  E 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 3 \\\text { C } & \cdots & 3 \\\text { D } & \text { B } & 4 \\\text { E } & \text { A,C } & 4 \\\text { F } & \text { B } & 4 \\\text { G } & & \\\text { H } & \text { E } & 5 \\\text { I } & \text { E } & 5 \\\hline\end{array}
-Using Table 3.3,what is the minimum number of activities that would have to be crashed in order to cause a decrease in the project's earliest completion date?


Definitions:

Same Individuals

Referring to using the same group of subjects or samples in different conditions or periods of a study or experiment.

Matched Pairs

A study design in which subjects are paired based on certain characteristics, with one subject from each pair receiving each treatment.

Parameter

A numerical characteristic or measure of a population, such as its mean or variance, which is often estimated using sample data.

Population

The entire aggregation of items or individuals from which samples can be drawn for statistical analysis.

Related Questions