Table 36 -Using Table 3

question 42

Multiple Choice

Table 3.6
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 9 C 10 D  A 4 E  B 12 F  C 5 G  B,D 6 H  E,F 7 I  H 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 9 \\\text { C } & \cdots & 10 \\\\\text { D } & \text { A } & 4 \\\text { E } & \text { B } & 12 \\\text { F } & \text { C } & 5 \\\\\text { G } & \text { B,D } & 6 \\\text { H } & \text { E,F } & 7 \\\text { I } & \text { H } & 8 \\\hline\end{array}
-Using Table 3.6,what is the earliest completion time of the project?


Definitions:

Budgeted Production

The planned level of output for a future period, determined as part of a company's budgeting process to forecast resource needs.

Estimated Inventory

An approximation of the quantity or cost of inventory that a company has on hand at a certain point in time.

Capital Expenditures Budget

A financial plan for a company's investments in long-term assets and major projects.

Direct Labor Cost

Expenses associated with employees who physically produce a product or are directly involved in providing a service.