Table 37 -Using Table 3

question 97

Multiple Choice

Table 3.7
 Activity  Immediate  Predecessor (s)  Time  (weeks)  A3 BAC4DA2EA,B4 F A, B,C2GD,E1HE6IE,F2 JG,H,I4 KH,I3 LI6\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \mathrm { A } & \cdots & 3 \\\mathrm {~B} & - \mathrm { A } \\\mathrm { C } & \cdots & 4 \\\\\mathrm { D } & \mathrm { A } & 2 \\\mathrm { E } & \mathrm { A } , \mathrm { B } & 4 \\\mathrm {~F} & \mathrm {~A} , \mathrm {~B} , \mathrm { C } & 2 \\\\\mathrm { G } & \mathrm { D } , \mathrm { E } & 1 \\\mathrm { H } & \mathrm { E } & 6 \\\mathrm { I } & \mathrm { E } , \mathrm { F } & 2 \\\\\mathrm {~J} & \mathrm { G } , \mathrm { H } , \mathrm { I } & 4 \\\mathrm {~K} & \mathrm { H } , \mathrm { I } & 3 \\\mathrm {~L} & \mathrm { I } & 6 \\\hline\end{array}
-Using Table 3.7,suppose activity D can be shortened from 4 weeks to 1 week.Assume all other activity times remain the same.How much shorter will the total project earliest completion time become?


Definitions:

Tectonic Plates

The dozen or so fairly rigid blocks into which Earth’s lithosphere is broken.

Earthquake Risk

The probability or likelihood of experiencing earthquakes in a given area, often associated with fault lines or tectonic plate boundaries.

High Risk Areas

Locations identified as having a significant probability of experiencing hazardous events, such as natural disasters or environmental threats.

Seismic Waves

Vibrations that travel through Earth's layers, caused by natural processes like earthquakes or artificial events such as explosions.

Related Questions