Table 37 -Using Table 3

question 113

Multiple Choice

Table 3.7
 Activity  Immediate  Predecessor (s)  Time  (weeks)  A3 BAC4DA2EA,B4 F A, B,C2GD,E1HE6IE,F2 JG,H,I4 KH,I3 LI6\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \mathrm { A } & \cdots & 3 \\\mathrm {~B} & - \mathrm { A } \\\mathrm { C } & \cdots & 4 \\\\\mathrm { D } & \mathrm { A } & 2 \\\mathrm { E } & \mathrm { A } , \mathrm { B } & 4 \\\mathrm {~F} & \mathrm {~A} , \mathrm {~B} , \mathrm { C } & 2 \\\\\mathrm { G } & \mathrm { D } , \mathrm { E } & 1 \\\mathrm { H } & \mathrm { E } & 6 \\\mathrm { I } & \mathrm { E } , \mathrm { F } & 2 \\\\\mathrm {~J} & \mathrm { G } , \mathrm { H } , \mathrm { I } & 4 \\\mathrm {~K} & \mathrm { H } , \mathrm { I } & 3 \\\mathrm {~L} & \mathrm { I } & 6 \\\hline\end{array}
-Using Table 3.7,suppose activity I is delayed,taking 8 weeks to complete instead of 2 weeks.Assume all other activity times remain the same.How much longer will the total project earliest completion time become?


Definitions:

HVAC System

Heating, Ventilation, and Air Conditioning system, responsible for managing the temperature, humidity, and air quality in buildings.

Direct Reply Letter

A written communication that responds specifically and directly to a letter or inquiry received.

Previous Correspondence

Written or digital communications, like emails or letters, that occurred between the same parties in the past.

Frontloading

The practice of placing the most important information at the beginning of a communication to ensure it is seen or heard first.

Related Questions