question 6

Multiple Choice

Table 3.9
All activity times for the project are in weeks.
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 345 B 579 C 2310 A  D 258 B  E 177 B  F 357 C,D  G 789 D,E  H 2610F\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & 4 & 5 & \cdots \\\text { B } & 5 & 7 & 9 & - \\\text { C } & 2 & 3 & 10 & \text { A } \\\text { D } & 2 & 5 & 8 & \text { B } \\\text { E } & 1 & 7 & 7 & \text { B } \\\text { F } & 3 & 5 & 7 & \text { C,D } \\\text { G } & 7 & 8 & 9 & \text { D,E } \\\text { H } & 2 & 6 & 10 & F \\\hline\end{array}
-Using Table 3.9,what is the critical path of this project?


Definitions:

Social Media

A digital platform that facilitates the creation, sharing, and exchange of information, ideas, and other forms of expression among users.

Empty Vessels

A metaphor often used to describe individuals or entities that lack content, knowledge, or ideas.

Stuart Hall

A prominent cultural theorist and sociologist known for his work on racial identity, media representation, and the encoding/decoding model of communication.

Beliefs, Values, Ideas

The foundational thoughts, principles, and ideologies that shape an individual's or society's worldview and behavior.

Related Questions