Table 39
All Activity Times for the Project Are in Weeks

question 132

Multiple Choice

Table 3.9
All activity times for the project are in weeks.
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 345 B 579 C 2310 A  D 258 B  E 177 B  F 357 C,D  G 789 D,E  H 2610F\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & 4 & 5 & \cdots \\\text { B } & 5 & 7 & 9 & - \\\text { C } & 2 & 3 & 10 & \text { A } \\\text { D } & 2 & 5 & 8 & \text { B } \\\text { E } & 1 & 7 & 7 & \text { B } \\\text { F } & 3 & 5 & 7 & \text { C,D } \\\text { G } & 7 & 8 & 9 & \text { D,E } \\\text { H } & 2 & 6 & 10 & F \\\hline\end{array}
-Using Table 3.9,what is the probability that the project will be completed in 24 weeks or less? You will need to refer to a standard normal table to answer the question.


Definitions:

Customer Demand

The desire and willingness of consumers to purchase goods or services at a given price.

Coordination

The organization of the different elements of a complex body or activity so as to enable them to work together effectively.

Functional Form

The specific mathematical relationship or equation used to describe how variables in a model are connected.

Corporate Organization

A structure of a corporation, detailing its hierarchy, management roles, and division of responsibilities.

Related Questions