Table 39
All Activity Times for the Project Are in Weeks

question 43

Multiple Choice

Table 3.9
All activity times for the project are in weeks.
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 345 B 579 C 2310 A  D 258 B  E 177 B  F 357 C,D  G 789 D,E  H 2610F\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & 4 & 5 & \cdots \\\text { B } & 5 & 7 & 9 & - \\\text { C } & 2 & 3 & 10 & \text { A } \\\text { D } & 2 & 5 & 8 & \text { B } \\\text { E } & 1 & 7 & 7 & \text { B } \\\text { F } & 3 & 5 & 7 & \text { C,D } \\\text { G } & 7 & 8 & 9 & \text { D,E } \\\text { H } & 2 & 6 & 10 & F \\\hline\end{array}
-Using Table 3.9,if the expected time for activity E is changed to 9 weeks,by how many weeks will the projects expected completion time increase?


Definitions:

Steals Bicycle

The act of unlawfully taking someone else's bicycle without permission with the intent to permanently deprive the owner of it.

FOB (Free On Board)

A term used in shipping agreements to indicate that the seller is responsible for goods until they are loaded on a transport vessel, after which the buyer assumes responsibility.

Delivery Ex-Ship

Delivery Ex-Ship (DES) is a term used in international trade that indicates the seller is responsible for delivering the goods to a designated port and the buyer is responsible for unloading.

Risk Of Loss

A legal principle determining who bears the financial burden if goods are damaged, destroyed, or lost during a transaction.

Related Questions