Table 114
a Company Is Attempting to Schedule Workers for the the Next

question 8

Multiple Choice

Table 11.4
A company is attempting to schedule workers for the next seven days. The daily requirements, in number of workers needed, are shown below.
 Day MTWTHFSSU Requirement 5484623\begin{array} { | r | c | c | c | c | c | c | c | } \hline \text { Day } & \mathrm { M } & \mathrm { T } & \mathrm { W } & \mathrm { TH } & \mathrm { F } & \mathrm { S } & \mathrm { SU } \\\hline \text { Requirement } & 5 & 4 & 8 & 4 & 6 & 2 & 3 \\\hline\end{array}
Each worker must work five days per week and must have two consecutive days off.
-Use the information in Table 11.4.What is the minimum number of workers needed if preference is given to the pair S-Su in case of a tie in the selection of off days?


Definitions:

Receivables Methods

Methods used by businesses to manage and account for money owed to them by customers for goods or services delivered on credit.

Due Date

The specified date by which a task, assignment, payment, or project is expected or required to be completed or submitted.

Interest Due

The amount of interest payment that is owed but has not yet been paid at a particular date.

Maturity

This term refers to the date on which a financial obligation (such as a bond or loan) must be repaid in full.

Related Questions