Completion Time (From Start to Finish)of a Building Remodeling Project

question 91

Multiple Choice

Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days.The probability that the project will be completed within 185 work-days is ______.