If an Activity Can Be Completed in 10 Weeks at a Cost

question 22

Multiple Choice

If an activity can be completed in 10 weeks at a cost of $3,200 instead of the normal time of 12 weeks at a cost of $2,400, then the crash cost per week for the given activity is _____.