How are direct and overhead costs assigned to cost objects under activity based costing systems?
Direct Costs Overhead Costs\begin{array}{llcc}\underline{\text {Direct Costs}}&\underline{\text { Overhead Costs}}\end{array}

a.  Allocate  Trace \begin{array}{ll}\text { Allocate } &\quad \text { Trace }\end{array}


b.  Trace  Allocate \begin{array}{llcc} \text { Trace }&\quad\quad\text { Allocate }\end{array}


c.  Allocate  Allocate \begin{array}{llcc}\text { Allocate }&\quad\text { Allocate }\end{array}


d.  Trace  Trace \begin{array}{llcc}\text { Trace }&\quad\quad\text { Trace }\end{array}