Examlex

Solved

At the Analysis Phase, Which Step Is Not Commonly Used

question 13

Multiple Choice

At the analysis phase, which step is not commonly used.


Definitions:

Scheduling

The process of organizing, planning, and controlling workloads and resources to complete tasks efficiently and within set timeframes.

Organising

The process of arranging resources and tasks to achieve a specific goal or operation efficiently, often involving planning, coordinating, and controlling resources.

Critical Path

The sequence of stages determining the minimum time required for an operation, especially in project management, identifying the longest stretch of dependent tasks and establishing the shortest possible project duration.

Immediate Predecessor

A term used in project management and planning, referring to an activity that directly precedes another activity in a sequence, without any intervening activities.