Wendy has been informed by the CIO that the project she is managing MUST be done by December 20th and must be fully tested and implemented by December 31st.She realizes that will mean she will have to prioritize the functionality and build the system to meet the core functions,even if that means something gets delayed until the next release of that system.She is practicing the 'timeboxing' approach to scope management.