Examlex

Solved

Special Test Cases When Validating a Laboratory Computer System Do

question 17

Multiple Choice

Special test cases when validating a laboratory computer system do which of the following?


Definitions:

Immediate Predecessors

Activities or tasks that must be completed directly before a subsequent activity or task can begin, in a project or process sequence.

Critical Path

The longest sequence of tasks in a project, which determines the shortest possible duration to complete the project.

Slack

The amount of time a task in a project can be delayed without causing a delay to subsequent tasks or the project finish date.

Activity Duration

The total time taken from the start to the completion of an activity or task within a project.

Related Questions