Brutus Construction Started Work on a New High Rise Building

question 32

Essay

Brutus Construction started work on a new high rise building on January 1, 2019. The project completion date is December 2021. The contract price is $54,000,000. The following are the actual costs incurred and estimates of costs to complete the project.
 Years  Actual costs incurred  Estimated costs to complete 2019$15,000,000$30,000,000202022,500,00022,500,000202117,500,0000\begin{array} { c c c } \text { Years } & \text { Actual costs incurred } & \text { Estimated costs to complete } \\2019 & \$ 15,000,000 & \$ 30,000,000 \\2020 & 22,500,000 & 22,500,000 \\2021 & 17,500,000 & - 0 -\end{array}
Calculate gross profit or loss for each year using the completed-contract method.


Definitions:

Preparing Résumé

The process of creating a document that summarizes one's work experience, education, and skills for job applications.

Prospective Employers

Organizations or individuals considering hiring someone, often evaluating candidates' qualifications and fit for a role.

Unique

Being the only one of its kind; unlike anything else, often used to describe distinctive features or qualities.

Functional Résumé

A type of résumé that focuses on skills and experiences rather than the chronological order of one's work history.

Related Questions