Examlex
In an MRP problem, A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. Initial inventory values for A is 100, B is 200 and C is 0. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 800 in period 9, what will be the planned order release for B in period 5?
Production Manager
A professional responsible for overseeing the production process within a manufacturing facility, ensuring that goods are produced efficiently, safely, and meet quality standards.
Responsibility Centre
A unit within an organization, such as a department or division, whose manager is accountable for specific financial and operational outcomes.
Controllable
Refers to costs or factors within a business that can be managed or influenced by decisions made by the company.
Uncontrollable
A term referring to factors or costs that cannot be directly controlled or influenced by decisions in the short term.
Q6: Poka-yokes are procedures that block the inevitable
Q13: From an operational perspective yield management is
Q18: The essential issue in satisfying customers in
Q22: You are hired as a consultant to
Q32: In a CPM analysis if you subtract
Q41: Plant A is located at the (X,
Q66: Which of the following is a dynamic
Q79: Assuming a 24 hour operation in a
Q82: ISO 14000 is primarily concerned with environmental
Q113: You want to develop a three-sigma R-chart.