At the End of Week 10, This Project Has Cost

question 16

Multiple Choice

At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars. At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.   A)  2.5 B)  2.1 C)  1.8 D)  1.5