Use the Earned Value Table to Determine the Cost Performance

question 58

Multiple Choice

Use the earned value table to determine the cost performance index given the indicated state of the project. Use the earned value table to determine the cost performance index given the indicated state of the project.   A)  0.89 B)  0.92 C)  1.09 D)  1.13