Use the Earned Value Table for Project Makeready to Calculate

question 65

Multiple Choice

Use the earned value table for Project Makeready to calculate the estimated cost to completion. Use the earned value table for Project Makeready to calculate the estimated cost to completion.   A)  $4,285 B)  $5,250 C)  $6,050 D)  $7,645