Use the Earned Value Table for Project Makeready to Determine

question 41

Multiple Choice

Use the earned value table for Project Makeready to determine the earned value at week 49. Use the earned value table for Project Makeready to determine the earned value at week 49.   A)  $4,950 B)  $6,050 C)  $4,155 D)  $5,250