A Project Consisting of Six Activities Is Shown in the Table

question 14

Multiple Choice

A project consisting of six activities is shown in the table. If the project manager decides to operate on a late start schedule, which of these days has the lowest resource requirements? A project consisting of six activities is shown in the table. If the project manager decides to operate on a late start schedule, which of these days has the lowest resource requirements?   A)  Day 21 B)  Day 18 C)  Day 24 D)  Day 15