A Project Consists of Four Activities with Information as Shown

question 57

Multiple Choice

A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project? A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?   A)  8.00 B)  4.24 C)  2.82 D)  5.56