A Project Consists of Six Consecutive Tasks That Have Average

question 49

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project. A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days)  as shown in the table. Use Newbold's method to determine the aggregated two sigma buffer for this project.   A)  44 days B)  6 days C)  17 days D)  9 days


Definitions:

Somatic Cells

All the cells in the body except for the germ cells (the ova and sperm).

Genes

The basic physical and functional units of heredity made up of DNA.

Zygotes

The initial cell formed when a new organism is produced by means of sexual reproduction, resulting from the union of an ovum and a sperm cell.

Somatic Cells

Any cell in the body that is not a germ cell (sperm or egg), making up the major part of tissues and organs.

Related Questions