A Project Is Represented by the Activity Durations (Estimated at 90

question 51

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology? A project is represented by the activity durations (estimated at 90% likelihood of completion)  and precedence requirements shown in the table. What is the overall duration of this project if it is managed using critical chain methodology?   A)  22.5 B)  24.75 C)  27.0 D)  33.75


Definitions:

Anticipated Outcomes

Anticipated outcomes are the expected results or consequences of an action or decision.

Ranking Items

The process of organizing items or options in a sequential order based on their value, quality, importance, or other criteria.

Criterion

A standard or principle by which something is judged or decisions are made.

Competent Leaders

Those who possess the necessary skills, knowledge, and experience to effectively guide and inspire a group towards achieving its goals.

Related Questions