A Project Has the Activity Duration and Cost Information Indicated

question 25

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the duration of the least expensive project possible? A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the duration of the least expensive project possible?   A)  38 weeks B)  37 weeks C)  36 weeks D)  35 weeks


Definitions:

Management By Exception-Active

A management style where the manager actively seeks out deviations from the norm or problems in order to take corrective actions promptly.

Intellectual Stimulation

The aspect of leadership that involves promoting innovation and creativity among followers.

Contingent Reward

A leadership strategy where rewards are given based on the performance or achievement of specific criteria.

Kouzes And Posner

A framework of leadership proposed by James Kouzes and Barry Posner that emphasizes five fundamental practices leaders engage in to be effective: model the way, inspire a shared vision, challenge the process, enable others to act, and encourage the heart.

Related Questions