A Project Has the Activity Duration and Cost Information Indicated

question 86

Multiple Choice

A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. What is the highest total cost for completing this project? A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. What is the highest total cost for completing this project?   A)  $14,250 B)  $13,950 C)  $13,550 D)  $13,150