What Is the Early Finish Time for Activity F Given

question 48

Multiple Choice

What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?   A)  15 B)  17 C)  19 D)  21