An Activity Has an Optimistic Time Estimate of 25 Days,a

question 49

Multiple Choice

An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?