A Project Has the Precedence Requirements and Activity Durations Shown

question 14

Multiple Choice

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities B, C, and D can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?   A)  11, 30 B)  7, 24 C)  11, 24 D)  7, 36


Definitions:

Sender's Priorities

The importance or urgency levels assigned by the individual or entity initiating communication, based on their objectives or needs.

Abstract Word

A type of word that denotes an idea, quality, or state rather than a concrete object.

Passive Voice

A grammatical voice where the subject of the sentence is acted upon by the verb, typically making the action's doer less prominent.

Placing Blame

The act of attributing fault or responsibility for a problem or wrongdoing to someone or something.

Related Questions