What Is the Slack Time for Activity B Given the Activity

question 79

Multiple Choice

What is the slack time for Activity B given the activity times and precedence requirements shown in the table? What is the slack time for Activity B given the activity times and precedence requirements shown in the table?   A)  10 B)  9 C)  8 D)  7