-Use the Network Diagram and Activity Lengths in the Nodes

question 96

Multiple Choice

  -Use the network diagram and activity lengths in the nodes to determine the slack time for activity D. A)  3 B)  2 C)  1 D)  0
-Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.