A Project That Is Exceptionally Risky Might Still Be Undertaken

question 46

Multiple Choice

A project that is exceptionally risky might still be undertaken by a firm if they have several other projects underway that are considered more of a sure thing.This approach to project selection is BEST described by the criterion called: