Table 8.18.1 A Toy Company Uses a Kanban System to Make a Make

question 88

Multiple Choice

Table 8.18.1
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is 0.250.25 day; average processing time is 0.150.15 day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 8.1. Using an efficiency factor of 5 %, calculate the number of kanban containers needed for the fastener.

Understand the influence of different activating and deactivating groups on the rate of reaction.
Draw and recognize the structure of intermediates and products in electrophilic aromatic substitution reactions.
Understand the core concepts of McCrae and Costa's Five Factor Theory.
Analyze personality traits using McCrae and Costa's Five Factor Theory.

Definitions:

Possible Selves

The aspects of the self-concept that represent individuals’ ideas of what they might become, what they would like to become, and what they are afraid of becoming.

Cognitive Theorists

Psychologists who focus on how our mental processes like thinking, perception, and problem-solving influence our behavior.

Incentives for Future Behavior

Rewards or punishments that influence an individual's likelihood of repeating specific behaviors.

Daily Impinging Information

The continuous flow of data and stimuli from the external environment that individuals encounter in their everyday lives.

Related Questions