Consider the MPS, BOM, and inventory data shown below.
Master Production Schedule: the following table shows the MPS start quantities.  Consider the MPS, BOM, and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities.   Bill of Material: - Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B. - Subassembly B uses 2 each of component E.  Selected Inventory Data:  \begin{array} { | c | l | c | c | c | }  \hline \text { Item } & \begin{array} { c }  \text { Lot Size } \\ \text { Technique } \end{array} & \text { Lead Time } & \begin{array} { c }  \text { Scheduled } \\ \text { Receipts } \end{array} & \text { On- Hand } \\ \hline \mathrm { B } & \mathrm { L } 4 \mathrm {~L} & 1 & 40 \text { in period 1 } & \\ \mathrm { C } & \mathrm { POQ } = 3 & 2 & & 40 \\ \mathrm { D } & \mathrm { FOQ } = 250 & 1 & \\ \mathrm { E } & \mathrm { L } 4 \mathrm {~L} & 2 & 160 \text { in period 2 } & \\ \hline \end{array}   Construct the MRP schedule using the above information. Bill of Material:
- Item A uses 2 each of component D, 1 each of component C and 2 each of subassembly B.
- Subassembly B uses 2 each of component E.
Selected Inventory Data:  Item  Lot Size  Technique  Lead Time  Scheduled  Receipts  On- Hand BL4 L140 in period 1 CPOQ=3240DFOQ=2501EL4 L2160 in period 2 \begin{array} { | c | l | c | c | c | } \hline \text { Item } & \begin{array} { c } \text { Lot Size } \\\text { Technique }\end{array} & \text { Lead Time } & \begin{array} { c } \text { Scheduled } \\\text { Receipts }\end{array} & \text { On- Hand } \\\hline \mathrm { B } & \mathrm { L } 4 \mathrm {~L} & 1 & 40 \text { in period 1 } & \\\mathrm { C } & \mathrm { POQ } = 3 & 2 & & 40 \\\mathrm { D } & \mathrm { FOQ } = 250 & 1 & \\\mathrm { E } & \mathrm { L } 4 \mathrm {~L} & 2 & 160 \text { in period 2 } & \\\hline\end{array} Construct the MRP schedule using the above information.


Definitions:

Graham Wallas

A social psychologist and educationalist who proposed one of the first models of the creative process in the early 20th century.

Creative Process

The series of thought patterns and mental techniques involved in producing new ideas or solving problems in innovative ways.

Illumination

Refers to the quality or state of being lit or the process of illuminating a specific area, often used metaphorically to mean clarifying or enlightening an issue or topic.

Keenness of Insight

The ability to see or understand things clearly and deeply, often leading to intuitive judgments.

Related Questions