Table 1018
a Company Desires to Set Up a Line to to Produce

question 104

Multiple Choice

Table 10.18
A company desires to set up a line to produce 60 units per hour.
The work elements and their precedence relationships are as follows.
 Work  Element  Time (sec)   Immediate  Predecessor(s)  140230135014402562625371538204,59186,710308,9\begin{array} { | c | c | c | } \hline \begin{array} { c } \text { Work } \\\text { Element }\end{array} & \text { Time (sec) } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline 1 & 40 & - - \\2 & 30 & 1 \\3 & 50 & 1 \\4 & 40 & 2 \\5 & 6 & 2 \\6 & 25 & 3 \\7 & 15 & 3 \\8 & 20 & 4,5 \\9 & 18 & 6,7 \\10 & 30 & 8,9 \\\hline\end{array}
-Use the information in Table 10.18. Suppose that a solution has been found to this problem with five stations. What is its efficiency?


Definitions:

Colles' Fracture

A type of fracture of the distal radius in the forearm with dorsal (rearward) displacement of the wrist and hand.

Distal End

The part of a limb or structure furthest from the body's midline or the point of attachment.

Skeletal System

The body system composed of bones and cartilage that provides structure, support, and protection, as well as enabling movement.

Rheumatoid Arthritis

A chronic inflammatory disorder affecting the joints, characterized by pain, swelling, and potential loss of function, primarily in the hands and feet.

Related Questions