Examlex

Solved

An Assembly Line Has to Perform 10 Work Elements, Whose

question 145

Multiple Choice

An assembly line has to perform 10 work elements, whose time requirements follow below. An operations analyst has found a solution using some heuristics. The solution follows below. Solution  Work  Elements  Time (sec)   Station  Work  Elements  Assigned  A 451 A, B, C  B 302 D, E  C 153 F, H  D 304 G, I  E 505 J  F 40 G 30 H 30 I 60 J 80\begin{array} { | l | l | l | l | } \hline \begin{array} { l } \text { Work } \\\text { Elements }\end{array} & \text { Time (sec) } & \text { Station } & \begin{array} { l } \text { Work } \\\text { Elements } \\\text { Assigned }\end{array} \\\hline \text { A } & 45 & 1 & \text { A, B, C } \\\text { B } & 30 & 2 & \text { D, E } \\\text { C } & 15 & 3 & \text { F, H } \\\text { D } & 30 & 4 & \text { G, I } \\\text { E } & 50 & 5 & \text { J } \\\text { F } & 40 & & \\\text { G } & 30 & & \\\text { H } & 30 & & \\\text { I } & 60 & & \\\text { J } & 80 & & \\\hline\end{array} If the cycle time of the line is 90 seconds, what is the efficiency of the assembly line?


Definitions:

Planning

The process of setting objectives and determining how to accomplish them.

Control Process

The systematic effort within an organization to guide activities towards meeting goals and objectives, typically involving establishment, monitoring, and adjusting of standards.

Performance Objectives

Specific goals and targets set for employees or departments to achieve, linked to the overall strategic objectives of an organization.

Secure Adequate Financing

The act of obtaining sufficient funds or capital necessary to support operations, projects, or investments.

Related Questions