Examlex

Solved

Activity Duration Estimation Becomes ________ as the Project Progresses

question 46

Short Answer

Activity duration estimation becomes ________ as the project progresses.


Definitions:

Operation of Law

Changes in rights, duties, or obligations automatically enforced by the legal system without the need for action by the parties involved.

Condition Precedent

A condition in a contract that must be met before a party's promise becomes absolute.

Avoidable

Capable of being prevented or circumvented through careful action or strategic planning.

Collateral Agreement

An agreement that has its own consideration, but supports another agreement.

Related Questions