Activity C Is an Immediate Predecessor of Activity G

question 14

Multiple Choice

Activity C is an immediate predecessor of activity G.Both activities have 4 hours of slack time.If both activities are delayed 3 hours, and these are the only delays, the overall effect of these delays is to delay the minimum project completion time by: