A Project Contains Activities D and K

question 29

Multiple Choice

A project contains activities D and K.Activity D has 5 hours of slack, and activity K has 7 hours of slack.If activity D is delayed 4 hours, activity K is delayed 6 hours, and these are the only delays, then the overall effect of these delays is to delay the minimum project completion time by:


Definitions:

Debt-To-Equity Ratio

A measure that compares a company's total liabilities to its shareholder equity, used to evaluate financial leverage.

Acid-Test Ratio

A financial metric that measures a company's ability to pay off its short-term liabilities with its quick assets (cash, marketable securities, and receivables), indicating liquidity without relying on inventory sales.

Book Value Per Share

A metric calculated by dividing a company's equity available to common shareholders by the number of outstanding shares.

Purchasing Inventory

Purchasing inventory involves the acquisition of raw materials, work-in-progress, or finished goods to ensure that production can meet demand without unnecessary delay or stockouts.

Related Questions