Discuss the Assumptions Required for Determining the Probability That a Project

question 9

Essay

Discuss the assumptions required for determining the probability that a project will be completed within a certain time period by using a normal distribution of the activity time along the critical path determined by mean completion times of the critical activities.Do you think they are realistic for most projects?