Consider the Following Activity Schedule Chart for a Maintenance Project

question 43

Essay

Consider the following activity schedule chart for a maintenance project.  Activity  ES  EF  IS  LF  A 0617 B 0505 C 614715 D 6101418 E 14161517 F 514514 G 14171417 H 14191621 I 10131821 J 17211721\begin{array}{ccccr}\text { Activity } & \text { ES } & \text { EF } & \text { IS } & \text { LF } \\\text { A } & 0 & 6 & 1 & 7 \\\text { B } & 0 & 5 & 0 & 5 \\\text { C } & 6 & 14 & 7 & 15 \\\text { D } & 6 & 10 & 14 & 18 \\\text { E } & 14 & 16 & 15 & 17 \\\text { F } & 5 & 14 & 5 & 14 \\\text { G } & 14 & 17 & 14 & 17 \\\text { H } & 14 & 19 & 16 & 21 \\\text { I } & 10 & 13 & 18 & 21 \\\text { J } & 17 & 21 & 17 & 21\end{array} A.What are the slack values?
B.Identify the activities on the critical path.
C.If the time is in weeks, what is the impact of a two week delay in activity D, H, or C?


Definitions:

Direct Labor-Hours

A measure of the amount of time workers spend on a specific task or production of a certain quantity of goods.

Manufacturing Overhead

All indirect costs associated with the production process, including utilities, rent for the production facility, and salaries of production supervisors.

Raw Materials

The basic substances from which products are made, typically used in the initial stages of the manufacturing process.

Work in Process

Inventory representing partially completed goods, which are still undergoing manufacturing processes.

Related Questions