Examlex

Solved

For Questions Refer to the Following Information:
a P=240.0004QdP = 24 - 0.0004 Q _ { d }

question 36

Multiple Choice

For Questions refer to the following information:
A municipal water utility employs quasi-fixed capital inputs-are the water treatment plant and distribution lines to homes-to supply water to 20,000 households in the community it serves. The figure below shows the cost structure of this utility for various levels of water service. Quantity of water consumption is measured in 1,000-gallon units per month. AQFC is the average quasi-fixed cost curve, and LAC is long-run average cost. Long-run marginal cost, LMC, is constant and equal to $4 per 1,000-gallon unit. The inverse demand equation is P=240.0004QdP = 24 - 0.0004 Q _ { d } .  For Questions   refer to the following information: A municipal water utility employs quasi-fixed capital inputs-are the water treatment plant and distribution lines to homes-to supply water to 20,000 households in the community it serves. The figure below shows the cost structure of this utility for various levels of water service. Quantity of water consumption is measured in 1,000-gallon units per month. AQFC is the average quasi-fixed cost curve, and LAC is long-run average cost. Long-run marginal cost, LMC, is constant and equal to $4 per 1,000-gallon unit. The inverse demand equation is  P = 24 - 0.0004 Q _ { d }  .   -Two-part pricing is a desirable method of pricing water because A)  it is more profitable for the utility company than average-cost-pricing (i.e., second-best pricing) . B)  deadweight loss is zero. C)  the deadweight loss is paid for by the users of water. D)  it easy to implement in practice. E)  both a and d
-Two-part pricing is a desirable method of pricing water because


Definitions:

Control Perspective

An approach focusing on the monitoring and adjusting of processes and strategies to achieve desired outcomes or objectives.

Revenue Variance

The difference between how much the revenue should have been, given the actual level of activity, and the actual revenue for the period. A favorable (unfavorable) revenue variance occurs because the revenue is higher (lower) than expected, given the actual level of activity for the period.

Cost Variance

The difference between the expected cost of a project or production process and the actual cost incurred.

Labour Efficiency Variance

A measure used in cost accounting to evaluate the difference between the actual hours worked and the standard hours expected to produce a certain level of output.

Related Questions