   -Karr Construction built a levee for the state of Mississippi over a three-year period. The contracted price for the levee was $3,000,000. The costs incurred by Karr and the payments from the state over the three year period are as follows:  \begin{array}{|l|c|c|c|r|} \hline & \mathbf{2 0 1 7} & \mathbf{2 0 1 8} & \mathbf{2 0 1 9} & \text { Total } \\ \hline \begin{array}{l} \text { Costs incurred by } \\ \text { Karr } \end{array} & \$ 600,000 & \$ 800,000 & \$ 200,000 & \$ 1,600,000 \\ \hline \begin{array}{l} \text { Payments from } \\ \text { Mississippi } \end{array} & \$ 1,200,000 & \$ 800,000 & \$ 1,000,000 & \$ 3,000,000 \\ \hline \end{array}  If revenue is recognized in proportion to the costs incurred by Karr, how much net income is reported in 2019? A) $1,200,000 B) $800,000 C) $600,000 D) $175,000
-Karr Construction built a levee for the state of Mississippi over a three-year period. The contracted price for the levee was $3,000,000. The costs incurred by Karr and the payments from the state over the three year period are as follows:
201720182019 Total  Costs incurred by  Karr $600,000$800,000$200,000$1,600,000 Payments from  Mississippi $1,200,000$800,000$1,000,000$3,000,000\begin{array}{|l|c|c|c|r|}\hline & \mathbf{2 0 1 7} & \mathbf{2 0 1 8} & \mathbf{2 0 1 9} & \text { Total } \\\hline \begin{array}{l}\text { Costs incurred by } \\\text { Karr }\end{array} & \$ 600,000 & \$ 800,000 & \$ 200,000 & \$ 1,600,000 \\\hline \begin{array}{l}\text { Payments from } \\\text { Mississippi }\end{array} & \$ 1,200,000 & \$ 800,000 & \$ 1,000,000 & \$ 3,000,000 \\\hline\end{array}
If revenue is recognized in proportion to the costs incurred by Karr, how much net income is reported in 2019?