(A) Construct a decision tree to help the power company decide what to do. Make sure to label all decision and chance nodes and include appropriate costs, payoffs and probabilities.
(B) Where should the power company build the plant? What is the expected cost?
(C) Suppose that a geologist (and his team) can be hired to analyze the fault structure at Chico Canyon. He will either predict whether an earthquake will occur or not. If the geologist is perfectly reliable, what is the most the company should be willing to pay for his services?
(D) Suppose that an actual (not perfectly reliable) geologist can be hired to analyze the earthquake risk. The geologist's past record indicates that he will predict an earthquake on 90% of the occasions for which an earthquake will occur and no earthquake on 85% of the occasions for which an earthquake will not occur. Given this information, what are the posterior probabilities that an earthquake will and will not occur, given the geologists predictions?
(E) Should the company hire the geologist if his fee is $1.5M?
Dyad
A two-person social group.
Triad
A three-person social group.
Stable
A condition or situation that is not easily changed or likely to move or fail, maintaining equilibrium or consistency over time.
Émile Durkheim
A French sociologist, one of the founding figures of sociology, known for his studies on social cohesion and the functionalism perspective.
Q10: A Poisson distribution is appropriate to determine
Q12: The sampling distribution of the mean will
Q24: Using the following data,what would be the
Q24: Any characteristic of a population unit is
Q25: The interval estimate 18.5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1387/.jpg" alt="The
Q38: Which of the following statements correctly describe
Q43: In the first step of setting up
Q62: The chi-square goodness-of-fit test can be used
Q100: The US local airport keeps track of
Q116: The variance of a binomial distribution for