Consider the Table Below with Information Regarding Each Activity, Immediate

question 33

Essay

Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  Activity  Immediate  Predecessors  Minimum  Time  Likely Time  Maximum  Time  A 679 B 4911 C  A 3912 D  B 2612 E  B, C 3510 F  D 479 G  E 4715\begin{array} { c | c | c | c | c } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} & \begin{array} { c } \text { Minimum } \\\text { Time }\end{array} & \text { Likely Time } & \begin{array} { c } \text { Maximum } \\\text { Time }\end{array} \\\hline \text { A } & - & 6 & 7 & 9 \\\text { B } & - & 4 & 9 & 11 \\\text { C } & \text { A } & 3 & 9 & 12 \\\text { D } & \text { B } & 2 & 6 & 12 \\\text { E } & \text { B, C } & 3 & 5 & 10 \\\text { F } & \text { D } & 4 & 7 & 9 \\\text { G } & \text { E } & 4 & 7 & 15\end{array}  Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  \begin{array} { c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Minimum } \\ \text { Time } \end{array} & \text { Likely Time } & \begin{array} { c }  \text { Maximum } \\ \text { Time } \end{array} \\ \hline \text { A } & - & 6 & 7 & 9 \\ \text { B } & - & 4 & 9 & 11 \\ \text { C } & \text { A } & 3 & 9 & 12 \\ \text { D } & \text { B } & 2 & 6 & 12 \\ \text { E } & \text { B, C } & 3 & 5 & 10 \\ \text { F } & \text { D } & 4 & 7 & 9 \\ \text { G } & \text { E } & 4 & 7 & 15 \end{array}     a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task. b. What is the expected duration of the entire project? What is the standard deviation of the project duration? c. What is the likelihood that the project will be complete in 26 minutes?
a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task.
b. What is the expected duration of the entire project? What is the standard deviation of the project duration?
c. What is the likelihood that the project will be complete in 26 minutes?


Definitions:

Structural Changes

Significant modifications or transformations within an organization's strategy, operations, or culture.

Globalizing Organization

An organization that is expanding its operations and influence beyond its domestic boundaries to reach an international or global presence.

Increased Grievance

Describes a situation where there is a rise in complaints or dissatisfaction, often within an organizational or social setting.

Technological Advancement

The process of developing new technologies and improving existing ones to enhance productivity, efficiency, and quality of life.

Related Questions